Dartford Junction, Kent: plan ahead for nine-day closure - 14 to 22 Feb 2026
 
Dartford Junction, Kent: plan ahead for nine-day closure - 14 to 22 Feb 2026
Posted by Chris from Nailsea at 21:04, 10th January 2026
 
From the BBC:

'Plan ahead' for nine-day closure, rail boss says

Image not available to guests
Network Rail said the £10m scheme was an "essential" track upgrade

A railway line will close for nine days over February half term for a £10m upgrade to the track, with passengers advised to plan ahead.

Network Rail said Dartford Junction was the busiest railway junction in Kent, with 650 trains passing through it each day, and work was taking place from 14 to 22 February to minimise disruption.

Replacement buses will be in operation and several stations will undergo work at the same time.

Chief operating officer for the South East David Davidson said: "We've deliberately chosen the half-term to minimise disruption as schools are on holiday and fewer people are commuting."

He added: "We will be making the most of the time available when trains are not running to carry out station refurbishments."

Image not available to guests
Replacement buses will be operating while the work takes place

Davidson said the alternative to the nine-day closure would have been carrying out the work over 30 weekends, adding that would have been "much more disruptive".

Buses will replace services between Gravesend and Dartford towards Crayford, Barnehurst, and Slade Green.

Services will run as normal into London along the Sidcup, Bexleyheath and Woolwich routes.

Preparatory work will take place on 7 and 8 February, and follow-up work is scheduled for 1 March and 5 April, with closures also planned on those dates.

Junction improvements include renewing "points" - the moveable sections of track that allow trains to change direction - and laying new track.

Station improvements include new tactile paving at Dartford station, replacing damaged fencing at Stone Crossing and refurbishing the accessible toilet at Greenhithe.

Swanscombe station will be deep-cleaned, and Northfleet will have new LED lighting, with additional customer information screens.


 
The Coffee Shop forum is provided by customers of Great Western Railway (formerly First Great Western). The views expressed are those of the individual posters concerned. Visit https://www.gwr.com for the official Great Western Railway website. Please contact the administrators of this site at admin@railcustomer.info if you feel that the content provided by one of our posters contravenes our posting rules. Our full legal statment is at https://www.greatwesternrailway.info/legal.html

Although we are planning ahead, we don't know what the future will bring here in the Coffee Shop. We have domains "firstgreatwestern.info" for w-a-y back and also "greatwesternrailway.info"; we can also answer to "greatbritishrailways.info" too. For the future, information about Great Brisish Railways, by customers and for customers.
 
Current Running
GWR trains from JourneyCheck
 
 
Code Updated 11th January 2025