| Potential for another platform at Iver Posted by MichalM at 12:01, 27th November 2026 | ![]() ![]() ![]() |
When Crossrail was being planned, was there ever any mention of a bi-directional line adjacent to Platform 4 (currently the freight loop) at Iver? This would be an extremely handy location for trains to terminate during disruption. West Drayton P5 is often used by freight accessing the Colnbrook branch line so it's not always possible to terminate trains there.
What work would be necessary to make a Platform 5 at Iver? Is some of the necessary infrastructure already in place or was provision not made for this?
| Re: Potential for another platform at Iver Posted by IndustryInsider at 12:30, 27th November 2026 | ![]() ![]() ![]() |
Welcome to the forum.
There was indeed initially a plan for it, but it was deemed unnecessary in the end. See the attached image dating from 2012/13 roughly.
Not sure as to whether it was going to act as a turnback, but it was going to become the Up Relief line and the existing Up Relief (through Platform 4) was going to become the 'Up and Down Loop' which would have presumably been able to act as a Turnback.
So, some of the infrastructure is already in place, but additional signalling and track upgrades would be required (as well as the face of the existing Platform 4 being built out to become the Platform 5).
Not a huge amount of work, but probably not worth the cost for the benefits.
| Re: Potential for another platform at Iver Posted by Chris from Nailsea at 12:33, 27th November 2026 | ![]() ![]() ![]() |
Many thanks for your first post, MichaelM, and a very welcome to the Coffee Shop forum.
CfN.